Count it for your job
Type your date. The page shows the deadline and the statute it comes from. Nothing you type leaves this phone.
The California rules behind these dates
- Preliminary notice: within 20 days after first furnishing work, to the owner, the direct contractor, and the construction lender. A direct contractor gives it only to the lender, and a laborer does not give one. A late notice covers only work from 20 days before it was served. §§ 8200, 8204.
- Claim of lien, recorded with the county recorder: a direct contractor, before the earlier of 90 days after completion or 60 days after a recorded notice of completion or cessation (§ 8412). Everyone else, before the earlier of 90 days after completion or 30 days after that notice (§ 8414).
- A lawsuit to enforce the lien is due within 90 days after recording (§ 8460). Public works follow different rules (§§ 9000 and after).
Full California calculator · How long to file a lien in California · All 14 state calculators
This is the California rule only. Notice and lien deadlines are different in every state. Dates are counted in calendar days.
Where the dates come from
- Cal. Civ. Code § 8200
- Cal. Civ. Code § 8204
- Cal. Civ. Code § 8412
- Cal. Civ. Code § 8414
- Cal. Civ. Code § 8460
Same rules as the California calculator page. Statute text checked October 18, 2026.
This is general information, not legal advice. Rules change. Check the current statute or ask a construction attorney in that state before you rely on a date. Job Clock does not file liens, mail notices, pull permits, or give legal advice.