The North Carolina rules behind these dates
- Lien agent: for improvements costing $40,000 or more, the owner names a lien agent, except for improvements to an existing single-family home the owner lives in (§ 44A-11.1). A Notice to Lien Agent has to be received no later than 15 days after your first furnishing (§ 44A-11.2(l)).
- Claim of lien on real property: filed with the clerk of superior court no later than 120 days after the last furnishing of labor or materials at the site (§ 44A-12(b)), and served on the record owner (§ 44A-11).
- Lawsuit to enforce: no later than 180 days after the last furnishing at the site (§ 44A-13(a)).
Full North Carolina calculator · How long to file a lien in North Carolina · All 14 state calculators
This is the North Carolina rule only. Notice and lien deadlines are different in every state. Dates are counted in calendar days.
Where the dates come from
- N.C. Gen. Stat. § 44A-11.1
- N.C. Gen. Stat. § 44A-11.2
- N.C. Gen. Stat. § 44A-12
- N.C. Gen. Stat. § 44A-13
Same rules as the North Carolina calculator page. Statute text checked October 18, 2026.
This is general information, not legal advice. Rules change. Check the current statute or ask a construction attorney in that state before you rely on a date. Job Clock does not file liens, mail notices, pull permits, or give legal advice.