How long do you have to file a lien in Georgia?

File the claim of lien with the clerk of superior court within 90 days after you finish the work or furnish the materials, and send a copy to the owner within 2 business days after filing.

Statute: O.C.G.A. § 44-14-361.1(a)(2) (HB 480, 2021, signed text)

Notice deadlines before the lien, and the lawsuit deadline after it, are on the Georgia page. Those dates depend on who hired you and the kind of property.

Get your Georgia dates

Georgia Notice to Contractor: 30 days

This answer is the Georgia rule only. Lien deadlines are different in every state.

This is general information, not legal advice. Rules change. Check the current statute or ask a construction attorney in that state before you rely on a date. Job Clock does not file liens, mail notices, pull permits, or give legal advice.